Hi All,

Just a small doubt I have here to ask :

Though my material ties to Network for direct consumption against NWA , Is there a way that I can bring the same material via Inventory control (for goods issue purposes) because the material quantities are huge and there is not enough space to put these materials and project requires to give custody of this bulk quantity to Warehouse.

Can this be possible either in standard or in customization?

Few Pointers:

With Q : Inventory G/L will hit to large extent ( #material valuation class and OBYC settings)

With N:  I can input my Project G/L manually

I can go with Non-valuated project stock to achieve the desired results but it offer some disadvantages also .

That's the reason I want to route these materials via a WH.

All experts can share their views on it.

Thanks & Regards

Saurabh

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member195427
Active Contributor
0 Kudos

Hello experts,

Kindly reply to this matter on this post only as some points were discussed already in the following post:

Kindly discontinue it from there and continue it here only.

Thanks & Regards

Saurabh

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Not Sure, but you may explore the Special Procurement Type available in SPRO-->Production-->MRP-->Master Data-->Define Special Procurement Type.

This Field is available in MRP2 view in MM03 and Proc. Param tab of the Component in CJ20n.

Hope it Helps!

Thanks and Regards,

Varshal Kachole

former_member195427
Active Contributor
0 Kudos

Hi

It looks close but I am not sure what settings I need to make in 'Special procurement types'.

Will check it though.

Thanks & Regards

Saurabh