on 01-26-2015 3:19 PM
Hi Friends,
We are currently on Solman 7.1 SP 12.
I want to config custom code management in the preparation step one managing system preparation i am getting the error
The BW Content Activation has not been finished yet. when i observed CCMS_BI_SETUP not scheduling in the system.
Kindly suggest how to proceed further to avoid this error.
Thank you,
Chowdary.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Chowdary,
The re-active the BW Content Activation and check the Background job.
or re-active the background job.
Regards,
V Srinivasan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try to re-active.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Chowdary,
You got to SOLMAN_SETUP -> Basic Configuration -> Configure Automatically -> Activate BW content
if any error Refer
SAP Note 2022565 - Error in Basic Configuration > Step 6 Configure Automatically > Activity Enable Solution Manager Usage - CCMS_BI_SETUP cancels when updating to Solman 7.1 SP11
Check this note 1806396 - Error "The job ccms_bi_setup is not yet executed, execute activity Setup BW" however setup BW
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srinivasan,
I am attaching the screen shot for error.
In ccm i am facing the below issue
I again run the basic config and step configure automatically previously it is suppose to be green while i am rerunning i am getting below error
and as observed when i execute the above steps CCMS_BI_SETUP not getting triggered only the job SMSETUP: DIAG_SM_BI_SETUP is running and finishing successfully.
Thanks,
Chowdary
Hi Chowdary ,
Is the Basic configuration step of the solution manager completed ?
Can you check in ST22 whether any shot dumps are present ?
Check SAP Notes 2107190 and 2005507
Manu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Manu,
Basic configuration has been done successfully. But i repeated the step Basic configuration configure automatically once i received the error, this time the step also come with yellow warning like The BW Content Activation has not been finished yet. and i am not getting any dumps in ST22.
Thank you,
Chowdary.
Hi Chowdary ,
The BI Job must be still running in your system . Can you check in SM37 . ( search from the date you last tried this ) . Also check for any old locks in the system also make sure that your client is opened in SCC4 ( check the recommendation below )
Check the following note resolution 3
2053937 - Common issues after upgrade to SP12 - SAP Solution Manager 7.1
Thanks ,
Manu
Hi Chowdary,
Is the issue resolved. also are you setting up the CCM for SAP or just with -in Solman.
If your seting up for SAP you can leave the Manage config and open up the Session under SAP service engagement and delivery and run through the wizard.
That way you don't have to go through the whole process of Managed systems.
Refer OSS note 1861798 - Advanced Remote Delivery - Custom Code Maintainability Check
Where in you have the required wizard to be run to setup the CCM.
Let us know if this helped you.
Regards,
Ram
User | Count |
---|---|
86 | |
10 | |
10 | |
9 | |
7 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.