on 01-22-2015 3:13 PM
Dear all
I have created a factory calendar with just one Workday with the idea of using it in a Shipping point because we want to gather all the shipments that day of the week. But in the system it seems that this calendar is not being considered. I have assigned the calendar to the Shipping point in customizing. We don't use calendars in the routes. Should I customize more points?. I don't konw what I am missing.
Thanks a lot.
Regards.
Hi,
The Factory Calendar which you have defined is applicable only to your shipping point and not your Customers right?
Check in OVLZ whether the calendar is available for your shipping point .
Regards,
SRK