Hi Experts
We are facing an issue where setup time of an operation is inflated to a very large number after the order is converted from APO. For example if we have std value for set up time maintained as 15 mins for op 0030, after conversion the set up time of op 0030 shows a very large random number such as 4,500 mins. I am unable to get to the root cause of the problem. Please advice . Thank you
Hi Ganpath,
Please check in the PDS PPDS (APO) side the Duration of the activity at Modes level! Please pay attention, the duration on APO side are in seconds.
Thanks.
Regards, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Santosh. Thanks for the suggestion
Its a multi-mixed resource. I see that this setup activity starts on 01/22 and end on 01/28. The set up activity time should have been just 12 mins. No down times maintained. I cannot figure out why this activity getting stretched out..I would appreciate any suggestions
Thanks Marius for help me investigate the issue. I really appreciate it. We are going to maintain a maximum interval between the setup activity and the produce activity and then activate the maximum interval parameter in the strategy profile. Note 445899 addresses this issue
Thanks again for your help