on 01-21-2015 1:43 AM
Hello All,
I am trying to get gATP to create a stock transfer order (or STR) in ERP using PP/DS functionality as described in SAPHelp link below:
SAP Library - Rules-Based Availability Check
I have performed the following steps:
Please note, at the moment we are not using PP/DS for anything else yet, so no other PP/DS specific configuration has been performed. Also, no CIF specific config from APO back to ERP.
During sales order entry, RB-ATP in APO is triggered, and correct rule etc. is determined.
Requirement date is 10 days from today to fall inside planning horizon.
After saving the order, no STO or STR is created in ERP or in APO.
No requirement visible in APO via transaction /SAPAPO/RRP3
Any idea where I am going wrong?
This is what my transportation lanes looks like:
This is my check instructions:
Any help will be appreciated!
Lukas
Hi Lukas,
Did you create CIF integration model (ECC to APO) for master data (locations, materials, work center, PDS PPDS, etc.) and transactional data (Sale Orders, ATP Check, pl.orders, purch.req, stock, etc)?
I can't see in your screen shot if you have product specific defined at transportation lane level!
You have to create publications from APO to ECC if you want to see the APO's results on ECC side!
However the first step is to see your demand (SO) on APO side!
Thanks.
Regards, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Marius,
Thanks for the help.
Yes I have CIF configured as follow:
I cant see PP/DS option in CIF?
I did not previously have product specific transportation lanes, but I have configured them now. If I re-test gATP I can see the SO demand in the sales order plant but still nothing in the source plant:
Sales Order Plant:
Source Plant selected during gATP:
Hi Lukas,
You have to create publications on APO side to be able to see something in ECC.
Please follow the path: SPRO - APO - Integration with SAP components - Integration via CIF - Basic setting for Data Transfer - Publications - Maintain distribution definition.
You have to create publication type for each location involved in your scenario. The logical system is the ECC logical system.
Be sure that in the Object Specific Settings the publication type have the status Always Retransfer.
Hope that can help you!
Thanks.
Regards, Marius