Hi Experts,

I am working on subcontracting process and subcontracting product is engineering to order in APO PPDS.

For example,

We have a product "TANK", which is configurable and manufactured at subcontractor location. The TANK's components are designed and varies according to sales order similar to engineering to order. We create order BOM for TANK for each sales order.

Example:

order BOM 1

TANK - Header

Flanged ball valve - Component

order BOM 2:

TANK - Header

Flanged butterfly valve - Component

Can you please let me know steps to create subcontracting process through order BOM.

In standard subcontract process, material BOM is maintained in production version, which is maintained in material master and subcontracting inforecord. Then PV and PIR are transferred to APO to created PDS at subcontracting location.

But there is no option create PDS at subcontracting location through order BOM.  We try to create PDS through curto_create_focus, but PDS is created at our location, not at subcontracting location.


Kindly let me know how to create PDS at subcontracting location thorugh order BOM.


Thanks and regards,

Mathu

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Experts, I would appreciate any help in this regard.

Thanks and regards,