Plant Maintenance Scheduling and Call dates

Former Member
0 Kudos

Hi Experts,

I have a multiple counter plan below are plan details :

Cycle - 16000 hr

operation type - OR

CntrOverReadg               -           65000

AnnualEstimate             -            8000

3 measurement Documents were created as per dates below :

14.05.2010 dated Measuring Document has counter reading 32000

28.05.2010 dated Measuring Document has counter reading 65000

25.04.2012 dated Measuring Document has counter reading 81000

last order generated on        -  25.04.2012

order confirmation date         - 09.05.2012

latest order generated on      - 14.01.2015

My issue is why next order is generated so early ?

Only thing which I have done is for this plan, a new item is added.

Please share your valuable views.

Accepted Solutions (0)

Answers (2)

Answers (2)

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Kiran,

You mention this is a multiple counter plan, what are your other cycles?

Former Member
0 Kudos

Sorry     My issue is why next order is generated lately ( it was expected in May 2014).

former_member223579
Participant
0 Kudos

Hi Kiran,

What is your call horizon?.

And wht are all the scheduling parameter u have given can you pls share. so that

we can check better.

thank you,