on 01-18-2015 7:09 PM
Hi,
I have setup POSC, the steps are Deconsolidation, Quality and Putaway. When Unloading and GR is completed, the system automatically creates two tasks:
a. since it is not mixed pallet, deconsolidation is skipped.
b. GRZONE to Quality bin with active status
c. GRZONE to Quality bin with waiting status
I have confirmed the active task, completed the UD in the quality workcenter and completed the HU process step. After which, system changed the waiting task as below:
d. Quality bin to Quality bin with active status
I was expecting the final bin to be proposed. Any help would be great.
Karthik
Hi Karthik,
Check your Putaway strategy and customization.
Check product master data and strategy.
check WPT and strategy customization.
Check POSC table with respect to WPT and step and source and destination.
Regards
Suraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.