cancel
Showing results for 
Search instead for 
Did you mean: 

Basic Start Date and Finish Date

Former Member
0 Kudos

Dear experts,

I created one notification on 12-01-2015,created shutdown maintenance order on 15-01-2015 and i have taken 3 materials for required operation.

i did not confirm the order on 15-01-2015.i confirm the order on 17-01-2015,now my basic start date and finish date showing current date.

please anyone explain this.

Thanks,

Sunil Boya

Accepted Solutions (1)

Accepted Solutions (1)

MTerence
Active Contributor
0 Kudos

Hi Sunil

Check your scheduling parameters in OPU7 for order type

Adjust Basic dates, adjust dep. requirements to operation date is been selected, so change to do not adjust, then system will work correctly.

Regards

Terence

Answers (0)