on 01-17-2015 11:14 AM
Dear experts,
I created one notification on 12-01-2015,created shutdown maintenance order on 15-01-2015 and i have taken 3 materials for required operation.
i did not confirm the order on 15-01-2015.i confirm the order on 17-01-2015,now my basic start date and finish date showing current date.
please anyone explain this.
Thanks,
Sunil Boya
Hi Sunil
Check your scheduling parameters in OPU7 for order type
Adjust Basic dates, adjust dep. requirements to operation date is been selected, so change to do not adjust, then system will work correctly.
Regards
Terence