Hi,

When I am trying to create sales order with 2 K.G for the next day delivery the schedule lines are confirming after 8 days.

I tried to change the schedule line from CP to CN to deliver on the next day but upon trying to save getting this message.

Please consider there is no MRP-Planning at this material entered

Message no. V1899

How can I get rid of this message and save the order with CN to deliver the goods to meet the customers requested delivery date.

Alex.

Accepted Solutions (1)

Accepted Solutions (1)

catherine_mckenna
Active Participant
0 Kudos

Hi Alex,

Please check whether there were any changes in the user-exits of
the includes MV45AFZZ and MV45AFZB.

In most of the cases user-exits are cause for such inconsistencies.


For example USEREXIT_SAVE_DOCUMENT_PREPARE in the include MV45AFZZ.

I hope this helps.

Kind regards,
Catherine

former_member201804
Participant
0 Kudos

Hi Catherine,

Thanks a million. Yes you are absolutely right.

I was getting this message from the include of MV45AFZA -

Regards,

Alex.