cancel
Showing results for 
Search instead for 
Did you mean: 

How to configure "Early Watch Alert/Report "in Solution Manager

sanjiv
Participant
0 Kudos

Hi Experts,

I have successfully install my solution manager & successfully configured system preparation , basis configuration & managed system configuration on my solution manger .

I have also add my satellite system (Quality System ) into solution manager & configured all steps .

everything is green status &  I have also execute report RTCCTOOL into my solman as well as my managed system everything is green .

Now i want configure/activate & schedule early watch report/ alert for solution & my satellite system.

i have no idea please guide step by step .

i am close to complete my roll out project & its very important for me .

Please help me.

waiting your reply on the same .

Thanks & Regards,

Sanjiv Kumar

Accepted Solutions (0)

Answers (2)

Answers (2)

manumohandas82
Active Contributor
0 Kudos

Hi

Please share your st02 screenshot

Thanks ,

manu

sanjiv
Participant
0 Kudos

Hi Manu,

I have resolved ABAP Dump error .

Now please guide me to configure EWA Alert .

Thanks & Regards,

Sanjiv

manoj_nayak2
Participant
0 Kudos

Hello Sanjiv,

If you have already completed EWA Management setup,

then please open a solution and try to add Logical component and save it.

Regards,

Manoj

sanjiv
Participant
0 Kudos

Hi All ,

I have added my solman  ABAP/JAVA Logical component into existing solution "SAP Solution "  with leading role of solution "Production System"  as shown below.


Now we have created new Solution " ERP Systems"

now my question is what solution role will i  assign to this new Solution Production or any other ??

or can i create different different  solution for my all systems like development / production etc.

Please guide me .

Thanks & Regards,

Sanjiv

manumohandas82
Active Contributor
0 Kudos

Hi Sanjiv ,

You can create as many solution as you want .  As you have  thought it will be better to create multiple solution as Production and Non production .,Because you will be using the solutions to Configure the EWA  and BPMON .

All the systems that are productive  shall be assigned to your New solution .

Thanks ,

Manu

manoj_nayak2
Participant
0 Kudos

Hi Sanjiv,

Creating Solutions and assigning roles it depends upon your landscape.

You can create a solution and assign related systems to that solution.


Creating  multiple Solutions allows you to take a few systems together and create EWA, Analysis, Alert monitor, GO-LIVE Upgrade, BPM, Service level reporting.

Regards,

Manoj

sanjiv
Participant
0 Kudos

Hi All,

Sorry for my late response , actually i was on leave due to some personal issue.

Today i will try above said solution  & update you the same.

Regards,

Sanjiv

sanjiv
Participant
0 Kudos

Hi Experts ,

I have successfully configured & scheduled EWA for My Solution Manager as per guidelines.

its successfully done.

But Now I have Created new Solution " ERP Quality System" & added logical component for my BFQ system  into this solution  as show below

I have configured EWA Configuration for this single solution ever week on Saturday and Sunday . 

Please see EWA Administration screen shot.

but when  i check in SDCCN there is no task is scheduled showing for Quality System.

I have check SDCCN in both system my solution manager as well as my quality system. but there is no scheduled is showing .

Please tell me what is the issue .

did i missed any steps ..

Please guide me.

Regards,

Sanjiv

Former Member
0 Kudos

Hi Sanjiv,

I believe you have solman 7.1 and steps are as below :

Go t0 t-code solman_setup --> Earlywatch Alert Management and follow the steps mentioned there.

TO check the reports, use sm_workcenter --> System Monitoring tab -> Reports

Regards,

Nikhil

divyanshu_srivastava3
Active Contributor
0 Kudos

Hi Sanjeev,

Refer below kba for EWA process.

http://service.sap.com/sap/support/notes/1907383

refer another linked kba in the above link which talks about SP10+ setup.

sanjiv
Participant
0 Kudos

Hi Divyanshu Sir,

Thanks for your help

i check the KBA & will update your if any issue.

Thanks & Regards,.

Sanjiv

sanjiv
Participant
0 Kudos

Hello Divyanshu Sir,

I Have successfully created new solution " ERP Systems" assigned my ERP ABAP System in it.

but when i click on maintain solution i am receive ABAP DUMP.

Category                              External Error

Runtime Errors                  EXPORT_BUFFER_NO_MEMORY

  1. CX_SY_EXPORT_BUFFER_NO_MEMORY

Date and Time                   14.01.2015           13:15:39

Short text

                                The EXPORT data cluster is too large for the application buffer.

                What happened?

                                Resource bottleneck

                                The current program "SAPLS_SOLAR_LIBRARY" had to be terminated because

                                a capacity limit has been reached.

                What can you do?

                                Please make a note of the actions and input which caused the error.

                                -

                                To resolve the problem, contact your

                                SAP system administrator.

                                With transaction ST22 for the ABAP dump analysis, you can analyze and

                                administrate termination messages, or store them for a longer time

                                period.

                Error analysis

                                An exception occurred that is explained in detail below.

                                The exception, which is assigned to class 'CX_SY_EXPORT_BUFFER_NO_MEMORY', was

                                 not caught and

                                therefore caused a runtime error.

                                The reason for the exception is:

                                This is probably due to a very large dataset, for which there are

                                insufficient resources in your installation.

                                The shared buffer can only store objects up to a certain maximum

                                size that depends on the (adjustable) total size of the buffer.

                                This maximum size was exceeded in the operation that was terminated.

                How to correct the error

                                You can increase the maximum size of the exportable objects by

                                increasing the size of the shared buffer. You define this through

                                the profile parameter rsdb/obj/buffersize.

                                You can find more information on this parameter using transaction

                                RZ11. However, remember that - for performance reasons - a single

                                object must not take up the largest part of the buffer so that

                                the maximum allowed object size is considerably less than the

                                total size of the buffer.

Please find below screen shot for your kind reference.

Please tell me how  can i solve this ABAP DUMP for further steps.

Thanks & Regards,

Sanjiv


divyanshu_srivastava3
Active Contributor
0 Kudos

Before doing anything, take a restart of solution manager once.

If you get this dump again, then you might have to consider to reconfigure rsdb/obj/buffersize parameter support your system needs.

sanjiv
Participant
0 Kudos

Hello Sir,

I have restarted my solman , & try again but m still receive same error.

now how to increase  rsdb/obj/buffersize parameter.

i mean to say any rule for this , & what is the value for this parameter.

please find current value of this parameters.

Dflt Value           4096

Profile Value       4096

Current Value      4096

now what is the new value i have to set , i mean to say any rule ...

My Ram Capacity    16 GB

Please guide me what is the new parameters value.???

Waiting your reply ..

Thanks & Regards,

Sanjiv

divyanshu_srivastava3
Active Contributor
0 Kudos

Read the dump and see how much is needed - just a fair idea.

Still you need to increase it, so make it around 50000 and check.

sanjiv
Participant
0 Kudos

Hello Sir,

I have set parameter & now when i click on existing solution. it appear new screen .

What is the next step.

Thanks & Regards,

Sanjiv

divyanshu_srivastava3
Active Contributor
0 Kudos

Follow the note that I have given to you.

That will help you in getting this done.