Budget/release was changed - rebuild availability control

Hi,

i'm working on PS module on a project and once i'm trying to copy my budget using IMCCP3 transaction, i've got the following warning:

Message no. AP_COPY010

Diagnosis

Automatic budget adjustments were carried out for measures (orders or WBS elements), or budget releases of WBS elements were automatically changed.

However, there was no automatic adjustment to the data of the availability control.

This is the case, even if activation type 1 (automatic activation during budget allocation) is set for availability control in the budget profile of the measure.

Procedure

Rebuild the data of the availability control for the measures that were processed, if necessary. To do so, you can use transaction CJBN (WBS elements) or transaction KO31 (orders).

The availability control has the be activated manualy , and my purpose is to get it activated automaticaly once I copy my budget.

Is there any clue why I've got this warning or how can I fix it ; to get the availability control activated with the copy budget transaction?

Best regards