Planned Order for SFG after MRP run MD02= MD61(Qty)+ VA03( Qty)

Dear Experts,
Need your help and suggestion to Map the requirements.
Bom design
FG---SFG--RM( 1:1 ratio)
FG needs to be planned by MTO, planning strategy 20, MRP type PD, Individual/collective requirement indicator=1.
SFG and RM needs to be planned by MTS, planning strategy 40, MRP type PD, I/C=2, Mixed MRP indicator=3 for SFG. Lot size=WB
Sales Order Qty FG=100, When MRP is executed by MD50, FG planned Order qty=100
For SFG, PIR=200, When MRP is run through MD02, Planned Order Qty=200+100=300
Client requirement is the Replenishment element of SFG after MD02 run should be equal to PIR qty only?
Planned Order SFG=200 only.
How can I de-link the Sales Order qty which is passing its requirement to SFG also?
Appreciate your reply
Best regards
Shailesh
replied

Shaliesh,

This is standard behavior of the system as for SFG there are 2 requirements one from FG Planned orders dependent requirement and Another from SFG PIR Requirement.

As already suggested check with Planning strategy 70 for Sub assembly where PIR can be consumed with production quantities.

Or else with the help of BADI MD_CHANGE_MRP_DATA you can control double requirements passed to SFGs.

BR
KK