on 01-12-2015 6:02 AM
hi experts.
I have some issues to issue raw materials in production order.
our customer will construct new plant P200. but there is no storage location in P200. so P200 has to use strage location of plant P100.
i know that issue plant and location of bom components can be changed in production order by manual.
but my customer wants issue plant to be P100 automatically.
is it possible to set the issue location of other plant in bom ?
thanks in advance.
Hi. You can use the Special Procurement in BOM item to select a different Plant.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
i took a test.
and the result is successful.
first, i made a special procurement key 91 in configuration for P200 plant.
procurement type : F
special Procurement : U
palnt : p100
As BOM compoents
withdr.alter.plant : check
issuing plant : p100
second, i set 91 on sp key field of bom component.
after that,
i created production order. and issue plant of order component was set the P100 automatically.