rounding value mismatched when generating schedule line via MRP

when system runs MRP, it generates 13pc schedule line, but the rounding value is 12 in material master MRP view 1


I have checked the change log for SA and material, no change happened on that period.


as far as I know and I also test to prove it:


if the round value is 12 in material master, when running MRP, it should generate 12pc or the multiple of 12 schedule line instead of 13pc.


could any expert help on this? thanks a lot for your help in advance.