ECP values in CJ30 (Inconsistency)

hi All,

We've recently started using ECP for our projects. ECP is done with Version 0. In CJ30, ECP values of ONLY WBS Elements which have Network – Activity are copied over to column 'Planned Total Version 0'. However, Budget values are displayed if FY – 2014 is selected for ‘Period’ (See attached).

Costing variant 'PS06 is assigned in 'Assign Costing Variant to Planning Profile'. Both Budget / Planning Profile have checkbox selected for 'Total / Annual' values. PrimCE Group - is added for Planning Profile.

Q-1:) What should be done to have all the WBSE Cost Plan values to be displayed in CJ30 even when ‘Overall’ is selected for ‘Period’ dropdown?. Pl advise.

Q-2:) Why don't the values Sum-up @ Top-level WBS even with Bottom-up scenario?.

Note: I believe if Q-1 is resolved, this will resolve Q-2 also.

-thanks