ECP values in CJ30 (Inconsistency)

former_member210673
Participant
0 Kudos

hi All,

We've recently started using ECP for our projects. ECP is done with Version 0. In CJ30, ECP values of ONLY WBS Elements which have Network – Activity are copied over to column 'Planned Total Version 0'. However, Budget values are displayed if FY – 2014 is selected for ‘Period’ (See attached).

Costing variant 'PS06 is assigned in 'Assign Costing Variant to Planning Profile'. Both Budget / Planning Profile have checkbox selected for 'Total / Annual' values. PrimCE Group - is added for Planning Profile.

Q-1:) What should be done to have all the WBSE Cost Plan values to be displayed in CJ30 even when ‘Overall’ is selected for ‘Period’ dropdown?. Pl advise.

Q-2:) Why don't the values Sum-up @ Top-level WBS even with Bottom-up scenario?.

Note: I believe if Q-1 is resolved, this will resolve Q-2 also.

-thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Please review the feasibility of the SAP Note: http://service.sap.com/sap/support/notes/1366990.


Hope it Helps!

Thanks and Regards,

Varshal Kachole

former_member210673
Participant
0 Kudos

hi,

Thank you for responding.

‘Total-up’ values issue (i.e., Q-2) is resolved by assigning ‘Value category’ to Cost elements. I missed this part of config. However, issue Q-1 still exists. Any thoughts?.

OSS Note refered above (1366990) is available ONLY in German?



-Thanks

varshal_kachole3
Active Contributor
0 Kudos

Hi,

You can request SAP to release this note in English.

Hope it Helps!

Thanks and Regards,

Varshal Kachole