hi All,
We've recently started using ECP for our projects. ECP is done with Version 0. In CJ30, ECP values of ONLY WBS Elements which have Network – Activity are copied over to column 'Planned Total Version 0'. However, Budget values are displayed if FY – 2014 is selected for ‘Period’ (See attached).
Costing variant 'PS06 is assigned in 'Assign Costing Variant to Planning Profile'. Both Budget / Planning Profile have checkbox selected for 'Total / Annual' values. PrimCE Group - is added for Planning Profile.
Q-1:) What should be done to have all the WBSE Cost Plan values to be displayed in CJ30 even when ‘Overall’ is selected for ‘Period’ dropdown?. Pl advise.
Q-2:) Why don't the values Sum-up @ Top-level WBS even with Bottom-up scenario?.
Note: I believe if Q-1 is resolved, this will resolve Q-2 also.
-thanks
Hi,
Please review the feasibility of the SAP Note: http://service.sap.com/sap/support/notes/1366990.
Hope it Helps!
Thanks and Regards,
Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.