Reg: Rescheduling of Purchse requistion/Planned orders

Dear Experts ,

Need your advise eon the following issue and let me know what configuration is required.

I have set MRP as background job and i am able to see none of the Purchase requisitions/ Planned orders getting reschedule .

I had 100 's of Purchase requisitions and planned orders as on 07.01.0215 which were nit processed , so was expected last

MRP run has to reschedule these elements (PR's and planned orders).which is not happening,

Still i am able to see the release date of all these elements as 07.01.2015 .Manually if i run MRP in foreground it is getting rescheduled.