on 01-08-2015 6:19 PM
I have client request that they won't create the ECC vendor master record until the bidder has been awarded a contract in SRM. We are using Extended Classic Scenario without PI, is following doable or any recommendation:
Thx,
Wendy
Hi Wendy,
As of after SAP SRM 7.0 EHP1, using business function- Supplier Collaboration: SRM_SUCO_1 you can automatically send vendors to ECC.
Now in your case if you deactivate it, this process becomes manual.
Where as you can create dummy/proxy vendor in SRM until that vendor becomes 'Winner', later you transfer vendor to ECC & replicate same in SRM as final vendor.
To change supplier in central contracts in SRM use transaction BBP_CTR_01.
I hope it helps.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Vinay,
Thanks, this really helps ! Question for using SRM_SUCO_1, is PI required? This is because we are in non PI environment. Also, in my original question, does Vendor replication from ECC -> SRM (update) work? What I would do is to create the vendor in ECC using the same vendor # in SRM, then replicate back to SRM, will that update the original local SRM vendor? If this works, we can save effort by using dummy vendor then change it in central contract.
Your reply is appreciated.
Thx,
Wendy
Hi Wendy,
for the scenario mentioned by Vinay PI is required, it is used for the vendor transfer from ROS to ECC.
"Also, in my original question, does Vendor replication from ECC -> SRM (update) work? What I would do is to create the vendor in ECC using the same vendor # in SRM, then replicate back to SRM, will that update the original local SRM vendor?"
Yes this is possible, but in a slightly different way. You can create your ECC vendor manually, and then you can edit the SRM supplier business partner and assign the backend vendor number on the supplier data tab under link to backend system. This will create the connection between your SRM and ECC vendors via the VENMAP table. Afterwards you can use BBPUPDVD as usual to update the SRM vendor data from ECC.
regards
Zoltan
Hi Paul,
the described functionality of editing the vendor linkage has been provided in the application exactly for such cases when an existing ECC vendor and an existing SRM business partner needs to be linked together. Whether you call it as a workaround, or best practice this is the only option in the scenario described by Wendy (beside of editing database tables manually).
regards
Zoltan