Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Copy Plan Values in Budget Values

Hi Gurus,

I planned on WBS element with CJR2 using three cost element. I want to copy plan values of only two cost element planned.

I use the transaction CJ30.

Is it possible? How can I do?

Thanks

Nicola

Former Member
Not what you were looking for? View more on this topic or Ask a question