Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Planning callendar


Hi Experts

I have got some doubts about planning calendar. If the  factory calendar is set  with Saturday and sunday as holidays ,

is the same setting could be applicable to Planning calendar ? If so if I want to violate this , how to achieve this?

    Second question is if I want to set first three days of each week as working days in a planning calendar , how to define calculation rule

to achieve this?

Thanks in Advance for clearing above doubts

Regards

Srinivas.

Former Member
replied

Hello Srinivas,

1. Per week one period and Three working days per period is two different requirement,

For per week one period you can achieve through :

Per Week one period

Calculation rule:

Weekdays :

Counter week day =1

Week day = 1 ( Every week system consider first Monday, one period created for per week)

Three days per Week

Calculation rule :  Weeks (week Days)

Select 1,2,3 : system consider first 3 days per week ( Three Period created in this case)

Both are different requirement

As working days in planning calendar pick from the factory calendar. If your factory calendar have only three days working per week,system behave accordingly that

2. Yes, for second question

System consider 1 day for first two period and for last period cover all day up to next period date.

I hope this information helpful to you

Thanks & Regards

Umesh Mali

1 View this answer in context

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question