on 01-08-2015 9:04 AM
Good morning.
Is there any way of having simultaneously multiple plants in MRP/Stock lists?
I have 53 plants, for which i need to see the stock situation in all of them, at the same time, if possible.
I have been across the following post,
but it requires the activation of business function LOG_PP_LMAN. Is there any way, after running MRP in all 53 plants,
to have a consolidated MRP/stock list without activating any business function?
Thank you very much, in advance, for your help and input!
Best regards,
Nikos Giannopoulos
Hello Nikos
As far as I know, this is the only way to do that. Otherwise, you may create your own report using BAPIs BAPI_MATERIAL_MRP_LIST and BAPI_MATERIAL_STOCK_REQ_LIST.
Nevertheless, I think that you should test the business function activation. Besides the cross-plant view on MD04 there are other useful functionalities introduced by this business function and I can't remember of any negative effect of that. See the documentation below:
SAP Library - Production Planning and Control
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.