How to assign consumable products to work center ?

Hi gurus,

Currently i am mapping a chemical industry project.

here i have to map consumable products to work centers.

EX- suppose for 10 ton of fished product they are using 10 bags and 10 pallets.

they want to make a track of consumable bags & pallets.

stategy MTS, Industry- PI,

I have made a planned order of 10 ton, for each ton 1 bag & 1 pallet have to consume automatically at work cener.

Si how to mapping this ?

please help me in this regard,

thanks in advance

Former Member
Former Member replied

Hi  Shiva,

   

As per your question If it is automatic assignment of bom component to particular workcentre & consumption automatically at the time of confirmation, then...

go to routing & select operation then click on component allocation.

After that system ll show U all bom component, select required component assignment to this operation & then click on assign button.

Pls check & confirm

Thx

Alok