MRP issue

Hello Experts,

I have come across this issue while running the MRP. I am not sure if this is how MRP is supposed to work. Our client is running an MRP for a item with the following:

In stock: 9

Committed:0

Ordered:99

Required Quantity :35

When MRP is run with the required quantity it come up with a recommendation for a quantity of 26. What is expect the system to do is take the PO for the 99 as something that should fulfill the required quantity of 35.

I really think this seems to be a bug.

Any ideas?

Thank you,


Chintan