Multiple Recipe (BOM) for a material

Hi,

In textile industry one process order passes to three department ( bleaching, dyeing & finishing).Each department will have a recipe (BOM) for chemicals.

The recipes are common and used in multiple materials. If i combine all 3 department BOM as single BOM then if there is any change in recipe (BOM) then in all materials BOM has to be changed. But if i keep separately then we can change exact recipe.

In standard is it possible to map this in SAP PP-PI? If so kindly guide me.

Regards / US

Former Member

Helpful Answer

by