on 01-07-2015 4:50 AM
Hi All
I Have a MTO process, the standard price of the FERT is 10 in material master. Total of the bom or sales order costing estimate is 7. Why when I GR Finish product it post a value of 10 not same as sales order estimate price (7) ?
How to I get it post at the EK02 or sales order costing price? and as standard sap which is correct? standard price in material master or EK02 price?
Thank you all
Hi,
You have to check the requirement class, it has the costing id as B and Valuation should be M. Then only system will post GR with sale order price i.e. EK02 price.
Regards,
Mukthar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
1. GR is always valuated at price/cost updated in Material Master...so system rightly doing
2. Codition EK02 is a statistical posting used for pricing procedure
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.