Production Order Operation Confirmations

I am looking into a new process for a customer whereby they have 4 Operations on a Production Order

  • Operation 0001
  • Operation 0002
  • Operation 0003
  • Operation 0004

Operations 0001 0002 and 0003 are not milestone operations and do not have to be confirmed in sequence. i.e. 0002 can be confirmed before 0001 etc.

Operation 0004 is a milestone operation, therefore once confirmed, any unconfirmed operations before it will be automatically completed.

What are the benefits/drawbacks of using CO11N vs CO1F or vice versa?

If I use CO1F to confirm 0002 before 0001, it looks as though 0001 will auto-confirm even though 0002 is not a milestone.

Is this Correct?

Regards,

Dave.