stop server ECC PRD

Hello friends

I have a question, I extend the standard extractor 2lis_13_vditm, add two fields, this extractor is used for various repositories companies from various countries, this change or adjustment will be done as a requirement for a country, it is a Rollout, and i know to be do some activities when to be transported to the production environment, but my question is this you need a window of time to stop the server ECC PRD these adjustments to standard extractor 2lis_13_vditm? since detenerel server would be the Christ because it is a corporate ECC server where all companies from other countries are, or is there some other way so that it is not necessary to stop the server ECC PRD?

Greetings.

Nando.

Former Member
Not what you were looking for? View more on this topic or Ask a question