on 01-06-2015 12:00 PM
I am using SAP Business One since 2008. Today in this year 2015, I want to find the WIP value of production on 31/03/2012. Is it possible to get this value ? If yes, then how to get it ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Yes. Run the Trail balance with WIP G/L Account and give the date parameter end date as 31/03/2012.
Thanks
With Regards
Balaji Sampath