Order start time

Hello,

In our SAP system do "backward in time" scheduling for process orders. Currently all work center are setup to run for 24x7 time.

Now we have few materials setup in system which required to start by 6am in morening but should stop by 6:30pm in evening. That means process orders of these materials should start at 6am and should stop by 6:30pm. Next order should start at 6am next day mrning. Because business don't do production of particular materials in evening time.

So my question to you expert is; what should I do to meet business requirements? Do I need to change work center working time to meet this requirements?

What if we have two materials running on same work center, one we can produce 24 hrs but second can produce from 6am to 6pm only?

Reply appreciated.

Former Member

Helpful Answer