Hi all,

I have set up 3 level: Unlocked, Reviewed, Approved In BPC System 10.0

But, when i change the workstatus, it notice: You cannot change the work status for "null"

I thinks the reason is the current status of all data is null, is not set to Unlocked. So i cannot change to another status

Please help me.

Thanks all!

Br.

Accepted Solutions (0)

Answers (6)

Answers (6)

Former Member
0 Kudos

Hi,

How did you access to "Change Work Status" pane in BPC 10.0 ? Which way did you use? If you help me, I will be so happy

Because I need help quickly

Thanks for your interest..

Best Regards

dinesh_veluru
Active Participant
0 Kudos

Hi Gulgun,

In excel>>EPM tab>> "SAVE data>> change work status

Thanks,

Dinesh.V

Former Member
0 Kudos

Thank you so much Dinesh

I'm so happy now

Best Regards

Former Member
0 Kudos

SAP BPC 10.0 have not the check Enable Work Status like 10.1.

I thinks it is the reason. To make the current status is Unlocked, what should i do?

Br,

Former Member
0 Kudos

Hi Duyen,

If you have recently updated owner property in your dimension then these changed may be not update in your BPF so kindly update your BPF steps and again deploy process template.

Regards,

Sushant

Former Member
0 Kudos

Hi Duyen,

One strange thing is current status is blank.


Go to SE16 check entries in "UJW_STATCODE" table.

Regards,

Sushant

Former Member
0 Kudos

Hi,

If entries are missing then follow the same steps given in below thread.

Regards,

Sushant

Former Member
0 Kudos

Thanks Arnold and Sushant,

My member CC_CD is a top node.

I setup my USER ID is OWNER property of all member

When change status, i tried with top node member or base member but the current status is still null

akos_beres
Contributor
0 Kudos

Are there multiple hierarchies in the cost center dimension?

Former Member
0 Kudos

Hi Duyen,

For more detail about work status go through below Document.

SAP BPC NW 10.0 Work Status Implementation Guide V3.pdf</title><meta content="text/htm...

Regards,

Sushant

Former Member
0 Kudos

Hi Duyen,

Please check work status setting for that particular step what you have chosen for the performer?

If you have chosen Owner then for the that specified member you are not owner because of that system throw error. for detail click on the "See Detail". It will show below message.

If CC_CD is a parent level member then maintain your USER ID in OWNER property for the  CC_CD member.

Hope this will help you.

Regards,

Sushant.

Former Member
0 Kudos

Hi,

is CC_CD a base member of the cost center dimension or a node? If it is a node, try with a base member.

Also, have you tried to change the status via Excel?

BR,