Event GR Posted is denied for the DBM Order - External service procurement

Dear Experts,

We are facing the below mentioned issue while trying to perform goods receipt for external service procurement.

Error - "Event GR Posted is denied for the DBM Order  -------XXX"

The error message is raised when the tracking number is maintained in the Purchase order of External servce,

If we remove the Tracking order (DBM Job order number) from Purchase order and then perform Goods receipt (MIGO) then the error does not exists.

Request you to help us with suggestion.

Regards,

T.R.S,Praveen

Former Member
Former Member replied

Hi.

We found the Status ID was missing in action PO_CREATED.

The issue got resolved after maintaining Status ID in the action PO_CREATED. Please find the below screen shot of the same.

Regards,
T.R.S.Praveen