Question With Actual Costs

Hi espert,

I have a problem with the Actual costs about a specific WBE element.

In the output of the  report 12KST1A the amount of the actual is different from the details lines item.

In the Table RPSCO there is three record of the actual , while after I have run the transaction CJEN the system return me 4 record of ACTUAL Costs.

After i go in table RPSCO and I see again 3 Record of ACTUAL COST.

The problem will be solved if also the 4 lines that i see after that i run the transaction code CJEN was stored in the RPSCO.

How i Can solve my problem? How it is possible that there is a difference between the CJEN and table RPSCO?

Thank You

Former Member
replied

The CJEN transaction reconstructs the RPSCO table to align it with the CO tables.  Make sure you run CJEN not in Test Mode, run it for real.  RPSCO and COEP frequently get out of sync.

To really dig into the problem compare table COEP entries for your WBS to RPSCO.   You can also compare RPSCO to the summary tables COSS and COSP.