I am very new for SAP, but i do have some theoretical background... hope the to gain experience in the battle field and with your answers!
This time i found out that QAS system has time Zone CET, but DEV has UTC-3. We are in Buenos Aires, so UTC-3 is the correct configuration. I ran stzac in QAS but Tx says that the client is closed for changes. That´s is OK. I suppose i need to forward or transport the change from DEV to QAS (if there ir any transport request). How can i find if there is a transport request for this? If there isn´t a change request can i build one without actually modifying the table? or do i have to open the QAS system in SCC4 and procede with the change? What if the change in QAS ask me for a transport request? I know that transport request need to be generated in DEV... right?
Regards!
Hi Andres,
Best way is to change the timezone in DEV which will prompt for a TR.
This TR can be imported to QAS.
Alternatively , you may open QAS client and execute STZAC and change the timezone.
I would recommend you to read through some best practises on changing the timezone settings.
Timezone changes best practices - Basis Corner - SCN Wiki
Regards,
Deepak Kori
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.