Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Enter Change Number - BOM has history requirement

Hi Friends,

In Production system While trying to change BOM components for particular material through CS02,i am getting the error message " Enter change number - BOM has history requirement" and found from the t.code CS03 that one of the component BOM status has been set as "3" (Active with History requirement)  and then i was trying to get the Change Number through tables AENR,AEOI and RESB, in fact i did not find any change numbers though  we made engeneering change management field as mandetory the configuration point of view.

Going forward could you please suggest how to execute CS02 t.code and need to change BOM status as "1" (Active).

And your quick response is highly appriciated.

Thanks & Regards,

Srinika

Former Member

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question