maintenance plan and call no's

mahesh_sappm
Participant
0 Kudos

dear all,

i created one maintenance plan based on counter(km),then i scheduled the maintenance order- for 8000 km

due to parts unavailability and man power i keep on restarting the plan.till date  i received call nos -7 with maintenance orders.

now my question is how to check the what is the counter difference between two maintenance orders,means i like to know for how many km maintenance is going on.

regards,

G.Mahesh

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member224809
Active Participant
0 Kudos

Hi,

  • In Maintenance plan, go to schedule calls tab.
  • Select the required call number.
  • And press call algorithm icon as below, you can get details start of cal and counter values.

  • If counter details not available in that screen press F8 for counter details or click

Regards

Varun

jogeswararao_kavala
Active Contributor
0 Kudos

Hello Mahesh,


You can compute this easily from MHIS table from fields Call No. (ABNUM) and CallCounterReading (ZYKLS). Difference between adjacent two ZYKLS readings gives you the Counter difference between two Calls (Maintenance Orders). You need to develop an Infoset Query to have this report. You can have Order numbers also into the report by using (joining) table MHIO.


Hope this is what you intend to know.


KJogeswaraRao