Mould

  1. Hi.. Experts

My client is having lots of moulds with the different cavity , so for scheduling maintenance plan on performance of mould which is the best option for scheduling via the Single Cycle Plan or Multiple Counter plan.

For Exp :-

Mould: - M1 require maintenance after every 1000 shots  & M2 require maintenance after every 1500 shots.

Having 1000 mould with the same parameter as above.

So if I go with the single cycle plan then I need to create separate maintenance plan for every equipment….

So suggest any better way to schedule ……….