Rptcurrency dimension is not updated in BW (BPC 10.1)

Dear all,

Please help me in identifying the cause for below error

When I update data via input schedule in BPC EPM (version 10.0 SP 20 .NET4), Value in 'Rptcurrency' Dimension is written as blank in BW.

(records where rptcurrency is displayed are the initial records saved and when new records are added for second time or if initial record are changed, value in rptcurrency field is taken as blank).

Please see below screenshot of data in BW.

Tags:
Former Member
replied

You need to install Support Package 9 for SAP BW 7.40

BPC SP is not an issue in this case.