SAP for Utilities Discussions
Connect with fellow SAP users to share best practices, troubleshoot challenges, and collaborate on building a sustainable energy future. Join the discussion.
cancel
Showing results for 
Search instead for 
Did you mean: 

EG42 - Any method to reverse proration?

Former Member
0 Kudos

Hi experts,

Any solution to reverse proration date? As user key in a wrong proration date.

Cheers,

Lawrence

1 ACCEPTED SOLUTION

Former Member
0 Kudos

Yup,

Execute the transaction again,and revert all the changes done and save.

The time slice should vanish.

If any meter reading was given as part of the process they would either vanish (talking about Reading reason 11 and 16) or change to 09- Control Reading.

Hope this helps.

Cheers,

Rakesh..

sapisurdg.wordpress.com

View solution in original post

1 REPLY 1

Former Member
0 Kudos

Yup,

Execute the transaction again,and revert all the changes done and save.

The time slice should vanish.

If any meter reading was given as part of the process they would either vanish (talking about Reading reason 11 and 16) or change to 09- Control Reading.

Hope this helps.

Cheers,

Rakesh..

sapisurdg.wordpress.com