on 12-29-2014 5:31 AM
Hi Experts ,
I read scn threads on above error but no suitable not found for my Problem .
My scenario is we have created Project with root WBS (billing element) - Created 3 levels of WBS > Network & activity assigned to WBS > Settelment rule (WBS ) assigned to Activity > Work center & Activity type for Labour are created & assigned to Acivity > Now out of three activity type two has been completed & confirmed by CN25 .
Now I want to do periodic settlement for current Period but system gives above error (Note :- profit center is assigned only to Project Defination )
Need help as son as possible . All points are checked from PS , CO & FI but no any solution found (error screen shot attached )
Thanks.
Hi,
May I know the Settlement Receiver in your case?
Thanks and Regards,
Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Mr Virendra B,
pl check while creating final asset for W.B.S.E the profit centre is missing .so system stops you
Regards
Ambarish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi virendra,
check settlement profile to receiver object what is the parameter to that is that allow or other if other then set as allow to those.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Virendra,
Do you have the profit center at the WBS level to which you are trying to settle the cost? Is business area and profit center both mandatory in your case?
Can you check the BA and Profit center combination for your WBS?
Please check with your FI counterparts as they should be able to guide you on this error.
Regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Virendra,
as far as I know document splitting makes Profit Center as a mandatory field while settlement. The combination of Profit Center, BA and cost center is checked while doing settlement.
If you haven't maintained any profit center at the WBS level then I believe system should allow you to enter it. Why are you getting a message that Profit center cannot be changed? Are you changing profit center at the Project level??
Please consult with your FICO guys to sort it..
regards
Sammar
Hi Virendra,
I think as you have cost posted to the WBS that's the reason system is not allowing you to enter the Profit Center. What you can do is change the error message to Warning and enter the profit center and then again make it error message.
Else at the back end in PRPS table go and enter the Profit center field.. I would prefer the first option..
After this try settling the cost and see how it goes..
if it still doesn't work check with your FICO guys..
Regards
Sammar
Hi Virendra,
Good to hear that. If you think your Profit center remains same throughout the project then you can substitute the PC from Project Definition to all the WBS elements.
If that's not the case then make Profit center as Mandatory field for user input so that this issue doesn't arise again..
Have a good start to the new year..
Cheers
Sammar
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.