Need to execute consolidation pack on the basis of Time selection

Hi Experts,

We need to execute consolidation package full year for budget consolidation. However we can't execute the standard consolidation package full year. User are using data manager linkĀ  to select period by period then execute. Is there any way can execute Consolidation package on the basis of time selection?

Regards,

Chandra

Former Member
Former Member replied

Hi Chandra,

if I assume that you are calling a standard script for the consolidation then you could, by adding a *FOR/*NEXT loop, allow users to select one or several periods at a time. Without this loop the standard script only works for one period.

Having said that, you talk about a process chain so I am not sure if there is something else apart from the standard consolidation being executed. And if it is, I would be unsure if a loop would still work.

To be able to give you a better answer I would need to know what the exact script is, i.e. the content of the log file (or files).

BR,

Arnold