on 12-28-2014 12:41 PM
Hi
Plz use the reference period any Monday in 2010 as 04.01.2010 in yr WSR. You refer 01.12.2014 and try to generate wsr from 01.01.2014.
Thanks,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi PremKumar,
Go to SM30 -> V_T511K --> Enter the country grouping in the pop-up
In the next screen check for payroll constant "OVERT" and enter the value for constant in the Value column.
The value should be like this ForEx: If you are calculation Overtime after 40 hours the value for OVERT should be 40. Also make sure the start and end date are current and valid.
Regards,
Hari
It does not work as you are expecting
Just check below
Holiday class 1 - Holiday which indicates that day type 1 Off/Paid
Holiday class 0 - Where it is applicable for working day and weekly off in such cases we define day type rule as Holiday class 0 is = Day type 1 Off/Paid then working day as well appear as Off/Paid since you wanted differentiate weekly off's we have to define all weekly off's with different holiday class which should not be "0" then we can show day type as Off/Paid or what ever we want
it depends on the holiday class of particular day.
Regards
Venkatesh