Hi frns,

please any one explain about " MAKE-TO-ORDER PROCESS". i need detailed documentation about MAKE-TO-ORDER and how to configure

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Raju,

<b>Make to order Scenario</b>

1. Make-to-order production is a process in which a product is individually manufactured for a particular customer. In contrast to mass production for an unspecified market where a material is manufactured many times, in make-to-order production a material is created only once though the same or a similar production process might be repeated at a later time.

2. You can use make-to-order production: (a) For branches of industry or products where a small quantity of products with a large number of different characteristics are manufactured (b) When a product has to be assembled particularly for a sales order.

3. Stock keeping is not usually carried out for products that are made to order. In companies using make-to-order production, the demand program only determines the production area, in which various variant types are produced. Depending on how you track the costs associated with make-to-order production, there are two ways to process make-to-order items during sales order processing.

(a) Make to order using sales order

(b) Make to order using project system (not relevant for SD application)

4. for make to order production using the sales order, all costs and revenues involved for an order item are held collectively at that item. A particular rule is used that can be changed manually to transfer costs to profitability analysis.

5. make to order production is largely a production planning configuration. It is also controlled by the requirements type, which is determined by three things

the strategy group (MRP 3) in MMR

the MRP group (MRP1) in MMR

the item category and MRP type (MRP 1)

6. Make-to-order production is controlled by the requirements type. The requirements type is determined on the basis of the MRP group (MRP1) and the strategy group (MRP3) in the material master record. In addition, a plant must be assigned for make-to-order items in the sales order.

<b>Reward if helps</b>

Regards

Sai

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

The Make-to-Order with Component Availability Check scenario is tailored to fulfill the specific production requirements of manufacturers of configurable products. The key feature of this scenario is that a component availability check is triggered for a requested product as soon as the sales order is entered into the system. Missing components are identified immediately and the earliest possible delivery date of the configurable product is determined.

The scenario is particularly suitable for configurable products such as personal computers, engines or other products from the high tech and machinery industries

http://help.sap.com/saphelp_47x200/helpdata/en/90/758534c960a134e10000009b38f83b/frameset.htm

With regards

Rajesh