Hi Gurus,

We use PPT1 and DS board in PPDS. Planners when they look into /N/SAPAPO/PPT1 Days of supply values

are not populating correctly for shelf life inventory which is expiring in MAY be in 9 or 3 months.

We are using shelf life planning and my heuristic respects the shelf life but dont days of supply.

Example:

Total shelf life is : 720 days

Min shelf life is :   270 days

When i run my heuristic system respects shelf life and  generate receipts if the inventory is expiring after 270 days even there is inventory.

I dont see the in days of supply when i am in PPT1

Please suggest how we can have days of supply respect shelf life and min shelf life.

Thanks in Advance

Regards,

Rajesh