Hi,

How should we arrive at what should be the settlement rule for PM order and service order.

Thanks

Former Member
replied

Hi Abraham,

It depends on your requirement, if your service order is generating revenue, then the difference between revenue and cost is settled. You can also refer below thread which was discussed earlier

How to not settle CS work order revenues?

Regards

Terence