MRP group has been assigned to MRP profile, and the profile has been assigned to the material.  When running the MRP, the profile is not considering the assigned MRP group (consist of pr type only).  Any idea?


Thank you,

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

a MRP profile is just another type of master data, let us say it is even above the material master. So it gives its values to the material master  like a material master gives it values to a purchase order. And like it is possible to overwrite values directly in the PO, it is possible to overwrite a MRP profile default with another value in the material master.

You have to think about your design. It is possible to define the MRP profile to protect the fields so that users cannot enter a different value in material master.