on 12-23-2014 9:41 AM
When assigning demand to resource it give error, earlier it was working but what happen suddenly don't know
No availability information for resource 90000038 after period 31.03.2015 exists
Message no. /MRSS/SGE354
Diagnosis
The assignment that you want to create ends in a period for which no availability transfer has yet taken place.
Procedure
Use report /MRSS/HCM_RPTWFMIF to transfer the availability information. Then update the planning board and create the assignment.
I already run above report but resource availability not coming.
Please guide
Resolved.