Reg : Sales Order costing

former_member184571
Participant
0 Kudos

Dear Experts ,

Need your inputs on the sales Order costing.

We are working in a MTO environment (Strategy group : 25 )

During sales order costing , Costs are rolled  incorrectly.

We are doing cost estimate at sales order level ( Multilevel BOM ).At the time of sales cost estimate (VA01) , for all these in-house produced material

system is fetching the price from standard from Material Master. The cost estimated for these components at sales order level is not picked for product

cost.What necessary settings has to be done from PP/CO side so that system should not fetch the standard prize from material indeed it has to consider

cost estimated at sales order level( Both material and operation costs)

Could anyone share what all the necessary settings required in requirement class (046) , requirement type(TAC) .

Regards,

Daya

Accepted Solutions (1)

Accepted Solutions (1)

former_member198650
Active Contributor
0 Kudos

Hi Daya,

Check the material valuation strategy maintained in the valuation variant. Whether you have defined standard price as first priority due to this it is picking the price in costing. Select Planned price 1 as first priority then try to do costing again.

Regards,

Mukthar

Answers (2)

Answers (2)

rajneesh_saxena
Active Contributor
0 Kudos

Hi

In requirement class 'w/o val str' should be blank and in costing section you need to do all settings as required by you.

Regards

Rajneesh Saxena

former_member184571
Participant
0 Kudos

Hi Mukthar/Rajneesh,

Thanks for your replies. Issue is resolved.

I will be closing this thread.

rajneesh_saxena
Active Contributor
0 Kudos

Hi Daya

You need to close the thread by hitting Correct answer or assumed answer. This is to keep the thread useful for others and also by doing this you follow rules of the forum.

Regards

Rajneesh

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

This is not a PP issue. Moving the thread to SAP Profitability and Cost Management.

BR

Caetano