Subcon Delivery not appearing in VL06C T-code

Hi Friends,

I have created a Subcon Delivery thru ME2O T-code and after that Picking is done in the delivery.

Now, I want to confirm the picking (as per BP documentation) in T-code VL06C.

But the delivery is not showing up. I have given the Shipping Point from Delivery as well as Picking and Planned Goods Mvt dates from the Delivery. but still it is not showing up. I even tried removing dates and just giving Shipping point, still no use.

What could be the issue here?

Also, I would like to the importance & usage of this t-code VL06C and want to know whether this is mandatory step to be followed after picking or can we do PGI directly.

Regards,

Sudhanva

replied

Hi,

Yes the screen shot says its is fully picked yes you can directly proceed for PGI .Seems it is confirmed for picking .That is why it is not coming into the transaction .

Regards,

0 View this answer in context
Not what you were looking for? View more on this topic or Ask a question