Copy Operator in Past Horizon

Former Member
0 Kudos

Hi Experts,

I have successfully used copy operator in the past horizon but not getting the results in the past horizon.

Use Case: Trying to copy actuals qty to adjusted qty for past 2 years. We have set horizon as 104 weeks and offset as 0 in the cop operator. We tried configuring horizon as -104 but copy operator does not take negative values in horizon.

Please advise.

Regards,

Aditya G

Accepted Solutions (1)

Accepted Solutions (1)

Irmi_Kuntze
Advisor
Advisor
0 Kudos

If you want to copy values in the past , than your offset must be negative.

E.g.:

PERIOD_OFFSET  -104

DURATION               104

would copy the last 104 month

YOurs

Irmi