Hi

for one of our projects we had planned revenue coming from a sales order quotation, this was removed from the quotation but the project plan/actual report still shows the planned revenue! I have run the transaction CJEN but this has not made any difference, any ideas on how I can remove the value from the PS report?

thanks

Joe

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Joe,

How do you remove the planned revenue from the quotation?

Also, what is your 'PS report'? What t-code?

Best regards, Gordon

former_member355038
Participant
0 Kudos

Hi Gordon,

The revenue was removed from the sales order quotation line item VA22.  The PS report used S_ALR_87013562 - sort by business transaction and value against BTran "Create quotation" is shown in the Plan Rev column.  Also the same value can be seen in CJ43 in the plan total column the same value is showing.

thanks for help

Joe

Former Member
0 Kudos

Hi Joe,

Thanks for info. Please refer to SAP note 98745, then you may reconstruct the project information system database RPSCO after performing the steps proposed by using transaction CJEN.

Best regards, Gordon